Skip to main content
Brisbane City Council · DA

299 CORONATION DR MILTON — Material Change of Use

View on BCC (opens in a new tab)

Source: Brisbane City Council Development.i (opens in a new tab).

Overview

Application no.A006721031
Address299 CORONATION DR MILTON
Application typeMaterial Change of Use
UseCommercial; food and drink outlet; multiple dwelling
Assessment levelImpact
ProgressIn Progress
StageDecision
Date submitted27 February 2025
Date decided
Public notification ends
Appeal resultNot Applicable

Assessment Stages

  1. Properly Made 3 March 2025
  2. Confirmation Notice 19 March 2025
  3. Information Request 26 February 2026
  4. Decision Notice Pending

Applicants

Primary applicantSilverstone Developments No 18 Pty Ltd
ConsultantUrban Strategies Pty Ltd

Documents

DAPublic-A006721031-20260527-75260 27 May 2026
Response to Public Notification 21 May 2026
Further Advice 21 May 2026
DAPublic-A006721031-20260517-10717 17 May 2026
Submission 8 May 2026
DAPublic-A006721031-20260429-09553 29 April 2026
notice of compliance with public notificat - 25 Apr 2026 25 April 2026
DAPublic-A006721031-20260424-86498 24 April 2026
DAPublic-A006721031-20260424-87091 24 April 2026
DAPublic-A006721031-20260421-67644 21 April 2026
DAPublic-A006721031-20260421-61524 21 April 2026
Air Quality Assessment 17 April 2026
DAPublic-A006721031-20260416-40161 16 April 2026
DAPublic-A006721031-20260416-41778 16 April 2026
Att B - Landscape Plan 30 March 2026
Att A - Proposal Plans 30 March 2026
Att C - Traffic Engineering Response Letter 30 March 2026
Att E - Waste Management Response Letter 30 March 2026
Att F - Office Market Analysis 30 March 2026
notice of intention to commence public not - 30 Mar 2026 30 March 2026
Att D- Swept Path Plan 30 March 2026
Response to Information Request 30 March 2026
Att G - Acoustic Report 30 March 2026
DAPublic-A006721031-20260309-26684 9 March 2026
Signed Extension to the Information Response Period 26 February 2026
Information Request 26 February 2026
DAPublic-A006721031-20260203-12666 3 February 2026
BCC ExtPeriod DAR 12.2 Information Request (incl s82) 2 February 2026
Att C - Landscape Plan 30 January 2026
Att B - Proposal Plans and Design Statement 30 January 2026
Att E - SWMP 30 January 2026
Att D - Civil Engineering Report 30 January 2026
Minor Change Request 30 January 2026
Att G - Transport Engineering Report 30 January 2026
Att I - Transport Air Quality Corridor Report 30 January 2026
Att F - Acoustic Report 30 January 2026
Att A - Code Responses 30 January 2026
Att H - Operational Waste Management Plan 30 January 2026
Extension to IR period 15 December 2025
APL ExtPeriod - Extend further agreed period 15 December 2025
DAPublic-A006721031-20251120-74597 20 November 2025
Amended Notice to Stop the Current Period 1 October 2025
Stop Current Period - Acknowledge 30 September 2025
Notice to Stop the Current Period 24 September 2025
Signed Extension to Information Request 4 September 2025
Architectural Design Statement Part - 2 3 September 2025
Architectural Design Statement Part - 3 3 September 2025
BCC ExtPeriod - Extend further agreed period 3 September 2025
Architectural Design Statement Part - 1 3 September 2025
Architectural Design Statement Part - 4 3 September 2025
Ext_IR 25 August 2025
APL ExtPeriod - Extend further agreed period 25 August 2025
DAPublic-A006721031-20250813-05799 13 August 2025
APL ExtPeriod - Extend further agreed period 12 August 2025
Att 1 - Proposed Plans Part-2 29 July 2025
Att 3 - Landscape Concept Plan 29 July 2025
Att 1 - Proposed Plans Part-1 29 July 2025
Development Summary 29 July 2025
App A - Code Assessment 29 July 2025
Att 2 - Architectural Design Statement 29 July 2025
Notice to Change Application 29 July 2025
Minor Change and Withdrawal of Notice About Stopping Current Period 25 July 2025
Key Improvements Presentation Rev B 28 May 2025
Stop Current Period - Acknowledge 16 April 2025
Notice to Stop the Current Period 15 April 2025
DAPublic-A006721031-20250413-17531 14 April 2025
Signed Extension to Information Request Response Period 1 April 2025
BCC ExtPeriod DAR 12.2 Information Request (incl s82) 31 March 2025
Confirmation Notice 19 March 2025
DAPublic-A006721031-20250317-45583 17 March 2025
DAPublic-A006721031-20250304-28392 4 March 2025
Proposed Plans Part-2 28 February 2025
Site Based Stormwater Management Plan Part-3 28 February 2025
Transport Air Quality Report 28 February 2025
Proposed Plans Part-1 28 February 2025
Traffic Report 28 February 2025
Serviceability Report Part-3 28 February 2025
Architectural Design Report Part-3 28 February 2025
Serviceability Report Part-1 28 February 2025
Serviceability Report Part-2 28 February 2025
Site Based Stormwater Management Plan Part-2 28 February 2025
BCC Lodgement Receipt 28 February 2025
Assessment Report 28 February 2025
DA Form 1 28 February 2025
Architectural Design Report Part-4 28 February 2025
Landscape Concept Plan 28 February 2025
Operational Waste Management Plan 28 February 2025
Proposed Plans Part-3 28 February 2025
Architectural Design Report Part-1 28 February 2025
Air Quality Review - Service Station 28 February 2025
Architectural Design Report Part-2 28 February 2025
Site Based Stormwater Management Plan Part-1 28 February 2025
App A - Code Assessment 27 February 2025

Comments · 0

Loading...

Loading comments...