Community Consultation request for Emma St precinct LATM project - New Design - Walter and Emma St
The petition
We, the residents of the Emma Street precinct in Holland Park West, raise serious concerns about the way the Brisbane City Council’s community consultation and administrative processes have been carried out in relation to the Emma Street precinct (Local Area Traffic Management) LATM project.
Residents support traffic calming in principle and recognise the importance of improving road safety. However, the community has not been given a meaningful opportunity to participate in the development of the new design.
In March 2026, a construction notice identifying a new design was circulated to residents in the Emma Street precinct. The new design differs significantly from the 2022 proposal previously circulated to residents. This lack of engagement has left directly affected residents excluded from the consultation process on a new design that will have substantial impacts on their street amenity, safety, access, and daily lives.
Specific concerns include:
- The placement of platforms in locations that were never previously identified in the 2022 proposal and in areas where residents have consistently raised as unsuitable, given their knowledge of the local conditions.
- The loss of at least 15 parking spaces on Navy Street as a direct consequence of the platform installation.
- The increasing traffic volumes generated by nearby facilities, such as new childcare centre, which has not been assessed or addressed in the new design, despite residents consistently raising concerns about speed, volume, and safety impacts on local streets.
- The absence of any road calming measures in the main feeder streets connected to Logan Road including Doughty Avenue, Crump Street and Swain Street.
The absence of any consultation on the new design contradicts the Council’s own guidelines and written assurances previously provided to directly affected residents that they would be consulted before any changes were finalised. This has not occurred. Residents believe that proceeding to construction without addressing these matters represents a significant oversight.
Lastly, residents express concern about the limited transparency and engagement from the local Councillor’s office throughout the approval process. Residents understand that the local Councillor has been directly involved in aspects of the project’s progression, yet legitimate questions raised over several months have not been met with clear or timely information about the new design or the basis for its approval. This lack of responsiveness and transparency has left residents with no option but to seek answers collectively through this petition.
We therefore request that Brisbane City Council immediately PAUSE further progress on the Emma Street precinct LATM project—particularly the traffic calming measures proposed for Walter Street and Navy Street—until a transparent, adequate, and meaningful consultation process has been undertaken with ALL directly affected residents.
Council response
Your petition raises concerns about:
Ongoing reports of rat running, speeding and general traffic safety concerns in the Emma Street precinct identified the need for Council to review local traffic conditions. The LATM project has been underway since 2022 to investigate and resolve these issues.
Between 30 September and 28 October 2022, community consultation was undertaken to seek feedback on potential traffic calming measures and the level of support for changes across the precinct. This included an online survey and opportunities for direct engagement with the project team. More than 147 submissions were received, with more than 60% of respondents supporting traffic calming measures, indicating general support to progress to detailed design.
The material shared during consultation only identified potential treatment locations and did not represent a final design. As the project progressed, community feedback was considered alongside further technical investigations assessing traffic volumes, speed data, safety performance, engineering feasibility, lighting requirements and network function.
This work identified that sections of Emma, Walter and Navy Streets were carrying higher-than-expected traffic volumes for local residential streets, including through traffic, along with elevated vehicle speeds. In response, the design was refined to focus on managing speeds and discouraging non-local traffic while maintaining access for residents.
In response, treatments were concentrated along this corridor to more effectively address these issues. Measures in other locations were refined or removed, supporting a coordinated approach focused on speed reduction, discouraging through traffic and improving safety outcomes.
The design also reflects changes in traffic conditions since 2022, including activity generated by the nearby childcare facility at Crown Street and Walter Street. For Walter Street, an engineering assessment determined that 2 speed platforms would provide a more effective response to rat running than the previously identified mountable roundabout near Crump Street. While a single mountable roundabout would deliver a localised reduction in speed, the adopted treatment forms part of a coordinated corridor approach to influence driver behaviour.
Individual changes to platform locations are generally not feasible where they would compromise design standards or reduce the effectiveness of the overall traffic calming outcome. The project relies on a coordinated network of treatments across the precinct rather than isolated measures. While not all locations identified during early consultation form part of the final scope, the adopted design focuses on areas considered to be most effective in addressing safety and traffic concerns.
The community was informed of the final design in March 2026 and upcoming construction in May 2026 through:
An internal review of the community consultation identified the information provided between the initial 2022 concept and the final design could have better articulated the changes made, including the rationale for changes made and the revised engagement approach. This review has highlighted improvements to how project changes and engagement processes are communicated in future.
The outcomes of this review have informed improvements to the communication of project changes and engagement processes in future initiatives.
Having considered this review alongside the technical investigations and community feedback, Council is satisfied that the planning, design development and engagement undertaken for this project are consistent with its policy and governance requirements. On this basis, and noting the current stage of delivery, it is not considered that pausing the works would provide a net community benefit. The project will therefore continue as planned to deliver the intended safety and traffic management outcomes for the precinct. In early June 2026, construction commenced and is expected to continue until August 2026, subject to weather and site conditions.