The petition

Residents draw to the attention of Council development application A006666182 seeking approval for a 16-floor development to be located on the site at 21-25 Glen Road, Toowong. This development is inconsistent with height allowances in the Toowong-Auchenflower neighbourhood plan. It is also inconsistent with principles in the broader City Plan for buildings and setbacks to make positive contributions to natural and built form, and to integrate landscape and building form to improve amenity of local communities. Proposed building height and setbacks will result in major overshadowing and overlooking of adjacent buildings of heights between 2 and 9 floors.

Finally, approving 28 units on this small parcel will further contribute to what is already a chaotic traffic and parking problem in Glen Road that will only be made worse when the Monarch development and the Green Bridge come online. Glen Road is a major active travel corridor to the University of Queensland and the inner western suburbs, and part of the Queensland government's Principal Cycle Network. This is a safety issue, and lives are at risk. Finally, approval of this application would be inconsistent with Council’s approval for only 8-floors at 44 Glen Road, a site that has 30% more land area.

Your petitioners therefore request that approval not be given to more than 8 floors on the site at 21-25 Glen Road, that setbacks are limited to those that reduce as much as possible overlooking and overshadowing of adjacent buildings, and onsite visitor parking is consistent with a building of this size.

Council response

Thank you for your petition requesting Council limit the development at 21-25 Glen Road, Toowong (the site) (application reference A006666182) to 8 storeys.

Council notes your concerns with the development at the site as follows:

As you may know, the site has a total area of 1,078 m 2 and is within a High density residential zone (up to 15 storeys), located within the Toowong residential precinct of the Toowong‑Auchenflower neighbourhood plan.

On 27 November 2024, Council received a development application for material change of use for the purposes of a multiple dwelling which was properly made on 11 December 2024, seeking approval for a 17-storey residential building with 28 residential units, 67 on-site car parking spaces and 2 basement levels. The development application was approved on 31 July 2025 after assessment against the requirements of the City Plan, and in accordance with the provisions of the Planning Act 2016 (the Act).

Relevant matters were considered in undertaking assessment of the development application in light of changed circumstances and the planning need for housing supply. The development was determined to appropriately respond to these changed circumstances since the adoption of the Toowong‑Auchenflower neighbourhood plan (first adopted into the superseded Brisbane City Plan 2000 in July 2012, and since incorporated into the current City Plan).

In addressing the assessment benchmarks in City Plan, the applicant provided a landscape concept plan, traffic assessment report, waste management plan, site-based stormwater management plan and architectural plans. The development was assessed as providing high‑quality architectural design outcomes, responding to a planning need by delivering housing supply via the renewal of an existing inner-city land holding and making efficient use of land.

The siting of the building and design of the built form was considered to avoid significant and undue adverse privacy and amenity impacts on adjoining development and residents. The development also provides onsite car parking that is compliant with the assessment benchmarks of City Plan and is demonstrated via a traffic impact assessment to not adversely impact the local road network.

The development application was subject to impact assessment which triggered a formal public notification process that occurred between 12 March and 2 April 2025. As part of this process, the applicant and properly made submitters were afforded appeal rights to the Queensland Planning and Environment Court in accordance with the Act. A total of 38 submissions were received. The matters raised by all submitters, including that of your petition, were carefully considered by Council as part of the assessment process.

You can view a copy of Council’s decision notice, the development application and approval documents online via Council’s Development.i website at developmenti.brisbane.qld.gov.au by searching application reference number ‘A006666182’.

Thank you for raising your concerns.