On behalf of many Moorooka and Tarragindi residents, I’ve submitted this petition for the City Council via Lord Mayor Schrinner and Deputy Mayor Adams to make safe as quickly as possible the very dangerous new intersection layout at the above listed location which was formerly a roundabout and which the community felt generally worked well. The new layout design is more dangerous for both drivers and pedestrians and needs immediate action to stop head on crashes in multiple directions especially cars exiting Beverley Hill St to Tarragindi Rd and for Homestead St traffic tracking down the hill where buses now must take up the whole road when turning left out of Tarragindi Rd to Homestead St. Pedestrians believe they are now more at risk too. Public consultation on it was very limited and needed to be much wider and more thorough.
Your petitioners therefore request action now from Lord Mayor Schrinner and Deputy Mayor Adams to ensure Moorooka and Tarragindi residents do not get hurt via road trauma as this is preventable but is inevitable if nothing is done. We also request also an immediate independent review of the process that led to this mess and how it happened to ensure it does not happen again.
Council response
Thank you for your petition requesting Council make safe then restore the roundabout at Fernvale Road, Homestead Street, Tarragindi Road and Beverley Hill Street, Moorooka (the intersection), and conducts an independent review into the project design to ensure community safety.
Council’s Local Area Network Improvements suburban works program (the program) delivers upgrades to suburban transport infrastructure to ensure our suburbs are safe and accessible for all road users, particularly pedestrians.
The intersection was identified by Council as a location where access and safety improvements would be beneficialfor road users walking, riding and driving through. Council’s assessments identified the existing roundabout was substandard according to current Austroads guidance, with visibility and pedestrian crossing points considered unsafe and not accessible for all community members.
Council’s road engineers completed a range of technical assessments to confirm the project design was appropriate, balanced pedestrian safety improvements with traffic flow through the intersection and minimised impacts to surrounding properties. Council found the necessary upgrades for pedestrian safety at this intersection were not possible within the existing roundabout arrangement without land resumption at nearby properties.
The project design included a new intersection alignment, three new pedestrian crossing facilities, line marking and signage for clear road delineation. This included kerb build-outs and refuge island installations for safe pedestrian crossing points, no stopping lines and other general line marking installations to improve sight lines on each approach to the new intersection and moderate vehicle turning speeds. As part of this design, the intersection configuration was redesigned to maximise safety for pedestrians while supporting the dominant traffic movements. This means the intersection is now configured with through movement between Fernvale Road and Homestead Street, however, the busiest turning movements between Fernvale and Tarragindi Roads are expected to operate similarly to the previous intersection arrangement.
Council recognises the new intersection is a change from the previous arrangement and it is normal to experience some delays as people familiarise themselves with the new traffic arrangements. Council expects this to settle over time as people become more familiar with the new intersection, which is supported by pre-construction traffic modelling.
The project team have undertaken numerous site inspections following the traffic switch to review the new intersection operations and are satisfied with its operation. This includes during peak periods, where Council understands higher than usual levels of congestion were experienced after the change. However, to ensure the new intersection is operating appropriately, Council will conduct a post‑installation study in the coming months.
When consulting on a project, Council is guided by our Community Engagement Policy . Council engages with residents, businesses and property owners who may be affected by the proposed works to understand their experiences and expectations through different levels of engagement. Community feedback is an important part of the program and is considered alongside our technical inputs to confirm the implementation of proposed treatments.
Council wrote to residents who live in close proximity to the intersection on 15 November 2022 to better understand their experiences.The consultation period occurred for two weeks from 15 November to 29 November 2022. This provided residents, businesses and property owners with an opportunity to provide their feedback through multiple avenues of communication including email, calling the project hotline or sending a letter by post.
Following review of this feedback and support from the local Councillor, the design was finalised to ensure safety concerns were addressed and the community were advised in March 2023 that works would progress to construction. This is in line with Council’s engagement processes for the program.
An independent assessment of the design was carried out in June 2023, which confirmed the intersection design was safe, compliant with all relevant design standards, improved pedestrian safety and has traffic flow comparable to the previous arrangement. Full findings of the independent review can be found on Council’s website at brisbane.qld.gov.au by searching ‘Fernvale Road, Homestead Street, Tarragindi Road and Beverley Hill Street upgrade’.
Based on the above and in the interest of safety, Council completed works in late June 2023 to deliver on the project’s important safety outcomes. Council appreciates the feedback received from the community on the new intersection arrangement. However, Council is confident this is an appropriate design that achieves the required safety improvements while balancing impacts on traffic flow and nearby properties. This design has been approved by a Registered Professional Engineer of Queensland, is in accordance with Austroads guidance and relevant standards, has been verified by a third-party technical review and is considered safe. Council will continue to monitor the site to ensure the intersection continues to operate effectively.