Keep developers fencing off public footpaths.
The petition
Make property developers keep the safety fences inside property boundaries and not on public footpaths. All developers with a small fee, to Council, can erect fences on public footpaths, blocking public access, without any consideration for public safety. This puts children walking to school, mothers with prams, people walking dogs, families walking and people excercising in danger of crossing roads unnecessarily or walking on roads around the blocked footpath.
All fencing to be removed from all footpaths, giving the footpaths back to the people who own them, the public.
Council response
Thank you for your petition requesting Council make property developers keep safety fencing within property boundaries and off public footpaths.
Temporary construction fencing is assessed prior to issuing any temporary closure permit by Council engineers. Council only considers requests for fencing to be located on the footpath to eliminate safety issues associated with the construction of the development or to upgrade the footpath and associated underground services conditioned as part of the associated development approval. Council assesses the length of the closure and seeks to minimise this as much as practicable.
While it may appear that the closures are solely to facilitate the development, they are required to allow upgrades to the footpath and utility assets at no cost to Council and rate payers.
Permits are generally identified in two categories, full or partial closure. Wherever possible, in high pedestrian traffic areas, Council does not support full closures and sets conditions to maintain a 1.2 to 1.5 metre-wide path on the verge. Footway permits are assessed against the Queensland Guide to Temporary Traffic Management (QGTTM)
Council normally requires the provision of a pedestrian path on the roadway with pedestrians protected by approved water filled barriers if a full closure is required for safety reasons associated with construction. Additionally, depending on the location of intersections, Council requires well signed footpath detours to direct pedestrians to navigate safely around the development frontage. In some cases, Council will condition the developer to employ traffic controllers to manage safe pedestrian movements.
Council limits footway permits to three monthly periods so that development progress and conditions can be reviewed, including community feedback, prior to any extension approval. Should Council receive negative feedback from the community Council officer would inspect the issue(s) and if the site contractor cannot address the problems to Council’s satisfaction, the permit may have more stringent conditions applied or the permit may be pulled immediately if necessary.Council works proactively with development sites to minimise temporary impacts on local communities such as temporary footpath closures.
Council encourages residents to provide feedback about specific footpath closures and these can be registered via Council’s 24-hour Contact Centre on (07) 3403 8888 and an officer will inspect the site to ensure the contractors are complying with all permit conditions.
The above information will be forwarded to the other petitioners via email.