The petition
Walter Taylor Bridge connects Indooroopilly and Chelmer in Brisbane. The bridge has facilitated cross-river travel for the people of Brisbane since the 1930s. However, the bridge may need an upgrade as the two lanes are a source of bottleneck for traffic during peak hours. During morning peak hour (7:00 am to 08:30 am), hundreds of cars line up to cross the Brisbane River on the south side of the bridge. Drivers on average wait 10 to 15 minutes to cross the bridge and the queue of cars usually stretches for hundreds of metres on Honour Avenue, Oxley Road and Longman Terrace. The bottleneck traffic is taxing on commuters and the environment. According to the Australian Bureau of Statistics (ABS), the median hourly earning is $36 per hour as of August 2020. Therefore, the cost of waiting 10 minutes in traffic is equivalent to $6 per driver and passenger/s. An idle car with its air conditioner on may use ~0.5 litres of fuel every 10 minutes, which is roughly $1. This is a preventable monetary cost to commuters with an unnecessary environmental impact caused by carbon emissions.
Assuming when the lights turns to green, cars get on the bridge at a pace of 1 car per second, then 60 cars are passing the bridge per minute. Assuming cars are queuing 2 hours per work day to cross the bridge, then that is equivalent to 7,200 cars queuing to cross the bridge per work day. Therefore, the estimated cost of bottleneck traffic on Walter Taylor Bridge to the local economy could be $12,600,000 per year (($6 + $1)*7200 cars*250 days). This does not take into account the cost to commuters' quality of life.
The petitioners therefore request the Brisbane City Council build a new two lane bridge next to the Walter Taylor Bridge to resolve current bottleneck traffic. The cost of building a new bridge featuring two one-way north and south lanes is affordable. The Eleanor Schonell Bridge (also known as the Green Bridge) between Dutton Park and St Lucia is two lanes, with a wide walking and bicycle path on each side. The Eleanor Schonell Bridge spans almost twice as long as the Walter Taylor Bridge and was built in 2006 for $55.5 million. Assuming the cost of building a bridge has risen 3% per year since 2006, this would be equivalent to a 60% increase in 2022. So a good estimate of building a new two-lane bridge next to the Walter Taylor Bridge would be $22.2 million (1.6*55.5*0.25). Based on the above estimations, the petitioners believe it is worth building a new two-lane bridge next to the Walter Taylor Bridge. From an economic perspective, the investment of building a new bridge can be paid off in less than two years by reducing traffic congestion. Construction of the bridge may also create more local jobs, improve the quality of life for commuters and reduce carbon emissions.
Council response
Thank you for your petition requesting Council construct a new general traffic bridge, to increase the capacity of the Walter Taylor Bridge crossing between Chelmer and Indooroopilly.
Council previously acquired the Witton Barracks site on the northern side of the bridge for parkland and heritage protection purposes, as well as to protect land needed to replace the Walter Taylor Bridge with a four-lane bridge when it reaches the end of its asset design life.
Council is currently undertaking a pre-feasibility transport planning study of the Chelmer to Indooroopilly river crossing in the vicinity of Walter Taylor Bridge. The study includesa combination of technical and community inputs to assist Council in determining the challenges and opportunities associated with increasing transport capacity across the river. The study will also help identify of further investigations that may be required. Community consultation was undertaken earlier this year via an online survey on Council’s website.
There is currently no budget or plan to build another bridge across the Brisbane River between Chelmer and Indooroopilly. The planning, design and construction of large traffic bridges is a very expensive undertaking requiring financial support from State and/or Federal Governments. The project to replace the Walter Taylor Bridge will be considered for funding subject to an assessment of its priority, against other similar citywide projects as part of Council’s annual budgetary process.
Thank you for raising this matter.