Hemmant Drainage
The petition
Residents draw to the attention of the attention of the Brisbane City Councillors the developers contributions for downstream drainage upgrades is rarely ever spent in the catchment where the developments have taken place. Hemmant and surrounds have been suffering flooding due to this neglect since the Brisbane City Council was formed in 1924. Terms like "cost benefit analysis", are no less than verbal garbage used by some bureaucrat to delay necessary drainage design and infrastructure works. The Brisbane City Council's 1992 Lytton Road East Development study carried out in secrecy with no community consultation clearly say that if the industrialization of Lytton and Hemmant were to take place substantial drainage upgrades were need to take place. Since that time massive amounts of fill have been placed in former inter-tidal areas between the rail line and Bulimba Creek and Brisbane River without and increased drainage or maintenance.
Your petitioners therefore request research be undertaken to tally up all developers contributions over the past 30 years in the Hemmant Creek, Lindum Creek and surrounding waterways and that amount be spent actually undertaking downstream upgrades which have actually been paid for by developers with any further delays.
Council response
Council continues to plan and deliver infrastructure for Hemmant and surrounding suburbs. Infrastructure may be delivered by Council or through the development assessment process. Council collects developer contributions (infrastructure charges) as part of the development assessment process, for example, when a subdivision or material change of use application occurs. Infrastructure charges contribute to providing essential higher-order (trunk) infrastructure for transport, community purposes and stormwater networks. Urban Utilities also collects infrastructure charges for water supply and sewerage networks.
Since 2001, Council has planned for future stormwater trunk infrastructure in the Hemmant area through a series of long-term planning instruments. Historic documents include the Australia Trade Coast South Infrastructure Contributions Planning Scheme Policy and the Brisbane Priority Infrastructure Plan. Prior to 2001, Council did not levy charges for stormwater infrastructure in the Hemmant area and developers were responsible for delivering their own stormwater infrastructure as part of their development.
Through the Queensland infrastructure charges framework, charges are capped state-wide and standardised since 2001. This framework removes the correlation between the charges and the infrastructure costs, demand and location. Revenue collected from a specific development may not be spent immediately or in that specific location. Funds may be accumulated and spent at a later time, or in another part of the city. This is to ensure that infrastructure is effectively prioritised so that it is delivered where and when it is most needed. Council is not required to hold infrastructure charges in trust.
Council is required to maintain a public Infrastructure Charges Register which can be accessed at the Infrastructure Charges webpage at www.brisbane.qld.gov.au/planning-and-building/applying-and-post-approval/infrastructure-charges . Since 1 July 2011, $6.9 million in infrastructure charges have been collected from developments in the suburb of Hemmant.
Council’s current capital works program, including trunk infrastructure, is supported by a number of plans including Brisbane City Plan 2014 (City Plan) the Local Government Infrastructure Plan (LGIP) and Long term infrastructure plans. The LGIP contains planned stormwater infrastructure items for the suburb of Hemmant, the provision of which will continue to be assessed against all citywide priorities in Council’s Annual Plan and Budget.
Since 2001, Council’s records identify that $21.3 million in trunk infrastructure has been delivered in the Doboy Ward, which provides a level of service to the suburb of Hemmant. This includes $218,468 for trunk stormwater infrastructure. Between 2010-2013 Council also delivered three minor (non-trunk) drainage works projects in Hemmant at a cost of $751,000.
The assessment and approval of development applications (DAs) are subject to provisions in City Plan, in particular, the Flood overlay code and Stormwater code require that development does not worsen flooding to neighbours. Council engineers perform thorough assessments of all DAs to ensure that they are compliant with City Plan by addressing flooding and stormwater matters adequately. It is standard practice for applicants to submit detailed hydraulic and stormwater reports, certified by a Registered Professional Engineer of Queensland, demonstrating that there are no adverse impacts to neighbouring properties.