The petition

The Cross River Rail project has asked Council to facilitate truck movements along Annerley Road at Cornwall Street and Kent Street, Annerley, by widening the intersections and other road works. The proposal fails to include any additional pedestrian or cycling facilities to allow safe crossing across Cornwall Street and Kent Street outside Dutton Park Rail Station, putting lives, especially children walking to school, at risk.

We the undersigned call on Brisbane City Council to refuse to widen the intersection at Annerley Road, Cornwall Street and Kent Street to facilitate 24/7 b-double and heavy vehicle truck movements as part of the revised Cross River Rail works plan. It is critical that Council provides a safe crossing point for school children, commuters, cyclists and local residents across Cornwall Street between Annerley Road and Kent Street, Annerley, and works with the State Government to deliver safer pathways to schools, public transport and the PA Hospital.

Council response

The Cross River Rail (CRR) project’s Tunnel, Station and Development contract incorporates the construction of a new underground rail link from Dutton Park to Herston and the construction of four new underground rail stations. The Southern Portal is proposed to be constructed between Dutton Park railway station and the new Boggo Road railway station, adjacent to the PA Hospital.

The CRR project is being delivered by the Cross River Rail Delivery Authority (CRRDA) and its contractors. The approval authority for the CRR project under the State Development and Public Works Organisation Act 1971 is the Coordinator-General (CG).

On 18 August 2020, the CRRDA applied to the CG to evaluate an eighth proposed change to the CRR project. The CRRDA’s Request for Project Change 8 (RfPC-8), requested the following.

- The use of Annerley Road, Cornwall Street and Kent Street, Annerley, as heavy vehicle access routes to the Southern Portal construction site.

- A whole of project change to remove the existing work time limitation of 10pm, where works were required to be undertaken after 10pm in accordance with road closure certificates granted by Council, and other approval from Queensland Rail.

The RfPC-8 was issued for public comment by the CG between 5 September and 2 October 2020. Following consideration of the submissions and additional material provided by the CRRDA, the CG approved RfPC-8 on 16 November 2020. Consequently, the approved changes now constitute the approved development for the CRR project.

Your request that Council refuse to widen the intersection at Annerley Road, Cornwall Street and Kent Street, to facilitate unrestricted B-double and heavy vehicle truck movements as part of the revised CRR work plan has been noted.

As the CG approved the RfPC-8 in November 2020, Council has no authority to amend or refute the new approved work plan.

Reference to heavy vehicles in RfPC-8 relate to construction vehicles that are allowed on Queensland public roads as-of-right. This includes semi-trailers, dump trucks, truck-and-dog and concrete trucks. Except in special circumstances, Council has no authority to prohibit the use of as of-right vehicles on public roads.

In regard to the approval of B-double vehicles for the Southern Portal work site. The RfPC-8 does not apply to the use of B-double vehicles for the Southern Portal site. A B-double permit is required for travel on a road outside of the approved B-double network. B-double permits are issued by the National Heavy Vehicle Regulator. Council is not aware of any proposal for the use of B-double vehicles for the Southern Portal work site.

The Project-wide Imposed Conditions for the CRR project requires the development and adherence to Construction Traffic Management Plans (CTMP), relevant sub-plans and individual construction activity sites. Consequently, the contractor for the Southern Portal is required to develop and receive approval for a site specific CTMP. The contractor must consult with and receive the approval of Council where there are impacts on local Council roads.

Council officers worked closely with the contractor in developing adequate and safe improvement measures as part of preparing the CTMPs to maintain the safety of pedestrians and cyclists during the construction period. These improvements, included in the approved CTMP, are summarised as follows.

- Provision of segregated bi-directional shared use pedestrian and cyclist path along Kent Street.

- Additional kerb ramps at the intersection of Cornwall Street and Kent Street, to improve pedestrian and cyclist access to the footpath adjacent to Dutton Park railway station.

- Relocation of existing taxi drop-off bay in Cornwall Street, to improve sight lines for pedestrians and cyclists.

- Installation of additional signage and threshold paint to aid safe pedestrian movements in Cornwall Street and Kent Street.

The above works resulted in a minor re-configuration of the intersection of Cornwall and Kent Streets, however there was no widening of the intersection of Annerley Road and Cornwall Street.

The request in RfPC-8 for extended work times beyond 10pm are intended to apply only to locations and situations where a relevant authority would normally permit night-time works (e.g. works on arterial roads or extended rail line track closures) or where the works involve continuous construction activities that could not be halted mid-construction (e.g. extended concrete pours). The request did not apply for nor was approval given for unrestricted construction activities on the whole of the CRR project.

In regard to your request for Council to provide a safe crossing point for school children, commuters, cyclists and local residents across Cornwall Street, between Annerley Road and Kent Street. Council officers undertook a preliminary review of the potential to provide a pedestrian crossing over Cornwall Street, between Annerley Road and Kent Street. However, given the very short distance between the two intersections approximately 25 metres, high vehicle volumes and limited sight distance from Annerley Road, the implementation of a non signalised pedestrian crossing is not considered feasible or safe at this location.

It is noted that signalised pedestrian crossings of Annerley Road are provided at the adjacent Annerley Road and Rusk Street; and Annerley Road, Cornwall Street, Nobel Street and Railway Terrace intersections.

Separate to the above, the section of Cornwall Street at the Annerley Road intersection was listed in the 2020-21 road resurfacing program, and this work was undertaken and completed in May 2021.

In regard to your request, that Council work with the State Government to deliver safer pathways to schools, public transport and the PA Hospital. Council is committed to making school travel safer by supporting several infrastructure initiatives to provide for children and school communities, and encourage safety on the roads around our schools. In particular, the Safer Paths to School program improves pathways and completes missing sections of footpaths to nearby schools. These improvements ensure teachers, students and families can get to school safer on safe and connected pathways.

As part of the CRR project, Council is working with the State Government to enhance pedestrian links to all new and existing public transport facilities along the CRR corridor. This includes the provision of a new pedestrian and cycle bridge between the PA Hospital and the Boggo Road railway and bus stations.