Fast-Track Lionel Turner Drive extension and connection to North Shore Bvld
The petition
Residents draw to the attention of Council:
Limited Access into and out of Bushland Beach. Currently, we only have 1 access point into and out of Bushland Beach to support the more than 6.5 thousand residents, in a rapidly growing suburb.
We the undersigned request that Council give consideration to:
We the residents of Bushland Beach request the Townsville City Council Fast track the extension of Lionel Turner Drive, Connecting it to North Shore Bvld. Currently, we only have 1 access point into and out of Bushland Beach to support the more than 6.5 thousand residents, in a rapidly growing suburb. It only takes 1 accident on Mt Low Parkway between the roundabout at Lionel Turned drive and the traffic lights at North Shore Bvld to shut down access into and out of Bushland Beach. These delays cause residents to be late for work and school, impede emergency services, and creates unnecessary frustration among residents. If by chance an emergency evacuation of the suburb was needed, it would be impossible to get all residents out and to safety in a timely manner.
Council response
Council at its meeting of 23 November 2022 adopted the following response to the ePetition:
In September 2021, a Petition was tabled at the Ordinary Council seeking Council to Fast-track Lionel Turner Drive extension and connection to North Shore Boulevard.
The current LGIP which commenced 2 March 2020 has identified the Lionel Turner Drive extension and connection to North Shore Boulevard as a 2025/2026 project within the LGIP.
In March 2022, the operation of the Mount Low Parkway / Lynwood Avenue / Lionel Turner Drive roundabout was reviewed using the latest traffic data. The analysis considered the traffic generation of the approved new developments comprising two childcare facilities, a service station, and a swim school with the existing background growth of residential development in Bushland Beach.
The outcome of this review confirmed the previous analysis undertaken to support the 2020 LGIP, specifically the review revealed the following:
• the increases in turning movement volumes at the roundabout as a result of the proposed developments are insufficient to cause a step change in the Level of Service currently operating at the roundabout.
• the proposed developments are not expected to have an unacceptable impact upon the performance of the Mount Low Parkway / Lynwood Avenue / Lionel Turner Drive roundabout from a capacity perspective; and
• the Mount Low Parkway / Lynwood Avenue / Lionel Turner Drive roundabout is expected to be operating within acceptable limits to at least 2026, both without and with the newly approved developments.
In June 2022 the CAPEX was prepared and the LGIP project has been identified as a project in the draft 2025/2026 schedule for consideration.
Council also made the following decision (at its meeting of 23 November 2022):
That the Chief Executive Officer arrange for a camera to be placed at the roundabout of Mount Low Parkway / Lynwood Avenue / Lionel Turner Drive for the month of February to allow Council to assess independently any accident data.