Local residents, parents and community affected by the proposed pedestrian safety enhancement on Taringa Parade for Indooroopilly State School insist on more consultation to find a simpler and safer solution

View on the council website (opens in a new tab)
Status: CLOSED, finished
Signatures: 246
Closed: 28 Feb 2019
Principal petitioner: Jayne Seebeck
ePetition number: 665

The petition

The concept design for the proposed pedestrian safety enhancements for Moggill Road and Taringa Parade at Indooroopilly State School (ISS) has been completed with NO meaningful consultation with the local residents and parents of children attending ISS. This is not aligned to the Brisbane City Council Community Engagement Policy 2016.

• For a $3m project, too few local residents, parents of children attending ISS and bush carers have been directly and transparently informed by the Brisbane City Council (BCC) of the situation, the scale of the selected solution, and the potential impacts or the changes that will result.

• Observations by local residents as well as current and past parents of children attending ISS conclude that the plan will not improve the identified pedestrian safety issues.

• Extending the issues along Taringa Pde could result in increased safety risks and increased traffic congestion. Plans do not include ongoing policing of motorist behaviour.

• The proposed Drop and Go zone will require the felling of many old growth trees – some over 100 years old. The ISS students’ great grandchildren would not see any replacement planting reach the current trees’ size.

• This section of trees offers considerable shade to children walking to and from the school, and those waiting for pick up.

• This section of trees improves the amenity of the area for local community.

• 15 years of bushcare work by volunteers to rejuvenate the area done at the direction of BCC will be wasted.

We, the petitioners, request that the plan be reconsidered and allow the BCC to undertake meaningful two-way consultation with local residents, parents of children attending ISS, and Bush Carers. We feel that a simpler and safer solution that will satisfy all affected by the plans can be found with community input.

Council response

Thank you for your petitions requesting Council undertake consultation with the wider community and reconsider the project design for the pedestrian safety enhancements on Moggill Road and Taringa Parade at Indooroopilly State School (ISS).

Taringa Parade is a two-lane district road that connects to Moggill Road via a signalised intersection. Moggill Road is a high-volume arterial road. The first segment of Taringa Parade is set as a school zone (40 km/h from 7-9am and 2-4pm) as it provides access to ISS, with two-minute pick-up zones (from 8-9am and 2-3pm) designated alongside both sides of the roadway. There were sixteen 90-degree car parks facing an embankment. These car parks were under a one-hour parking restriction from 7-10am during school days. There is a designated school crossing zone approximately 10 metres north of the car parks.

The previous drop-off and pick-up facility operated unsafely. In May 2017, one of the school’s students was injured as a result of being hit by a car outside of the school. Vehicles often parked up to three abreast in school peak times, with drivers regularly performing unsafe manoeuvres to return to the Moggill Road intersection after dropping off and picking up students. Infrastructure measures were required to manage the interaction between traffic and pedestrians in the vicinity. This upgrade encourages drivers to U-turn at the dedicated roundabout at Waverley Road, which is a safe manoeuvre for all road users in this area.

This safety upgrade was delivered by Council, on behalf of the Australian Government, through the Department of Infrastructure, Regional Development and Cities. This safety upgrade was fully funded by the Australian Government. Council has previously investigated the provision of a pedestrian overpass. At that time, funding was not received to construct the pedestrian overpass. Since then Council investigated alternative options to improve safety in the area and ISS was identified as a location in the local school network that required works to improve safety. As a result, Council identified a way of facilitating safe movements in the area with the project design.

The project scope included the construction of a dedicated service road, which operates as a drop and go area during school peak periods and car parking area outside school peak periods, as well as providing better access from the school to Taringa Parade with a left-turn only, north of Thorpe Street.

In order to facilitate the design, Council obtained approval from the Queensland Government on 11 December 2018 to acquire 131 square metres of Government-owned land. To mitigate any impacts, Council has dedicated 135 square metres from Council’s road reserve to Moore Park. This meant that there was no net loss of parkland.

To undertake this upgrade, 92 plants and shrubs and 37 trees were removed from the park. However, 148 new trees have been planted in the project site and local area, meaning for every tree removed, four trees were re-planted. An additional 1,116 plants and groundcovers were planted in the wider project area.

On 8 November 2017, a letter advising of upcoming investigation and survey works was distributed to the local community. Two more letters advising of additional investigation and survey works were also distributed to the community on 20 December 2017 and 6 July 2018. The letters outlined the work hours and scope of works of the investigation.

A project introduction letter with the concept plan was distributed on 15 January 2019 from the Walter Taylor Ward Office to approximately 320 residents and businesses. The project introduction letter included a direct project hotline number and email address through which the community can contact the project team. The project introduction letter included a direct project hotline number and email address through which the community can contact the project team.

Council discussed the project design with Taringa Parade Bushcare Group on 18 January 2019. Council also requested to work with the Taringa Parade Bushcare Group on the replanting program once the project was complete. The project team did not receive feedback about the replanting program from the Taringa Parade Bushcare Group.

A start of construction letter with the project plan was distributed to the community on 12 February 2019. A direct project hotline number and project email address were provided in all communication materials to allow the community to ask questions and provide feedback.

ISS also sent out information regarding the project via school newsletters and emails.

The project has now been completed and further consultation has been deemed unnecessary. An end of project letter has not been distributed to the public.

Thank you for raising this matter.