PROPOSAL FOR PUBLIC WORKS - Construction of a retarding basin within the existing open space including ancillary works, road grading and pipe upgrades to the surrounding streets. Replacement of the existing playground with new equipment, landscaping and associated works.
Key dates
Lodged
29 June 2021
Representations open
25 August 2022
Representations close
14 September 2022
Decided
24 November 2022
Original and amendments
S141A:Approved with conditions · Lodged 29 June 2021 · Representations 25 August 2022 to 14 September 2022 · Decided 24 November 2022
Original:Approved with conditions · Lodged 29 June 2021 · Representations 13 July 2021 to 2 August 2021 · Decided 24 November 2022