INLAND RAIL - Inland Rail risk assessment, contingency methodology and consultant involvement

View on aph.gov.au (opens in a new tab)
Status: Answered, finished
Asked by: Senator Bridget McKenzie
Portfolio: Infrastructure, Transport, Regional Development, Communications, Sport and the Arts
Agency: Inland Rail Pty Ltd
Round: 2026-27 Budget estimates
Question No: SQ26-000638
Asked: 25 May 2026
Answer due: 16 July 2026

Question

Ms McDougall: The contingency for risk was assessed at a work package level. We performed a detailed qualitative assessment, and then a quantitative risk model was used to determine the risk and contingency allowances. What's really key in determining that risk contingency is where the project is up to and its maturity status-so whether it's got the environmental approval, secondary approvals et cetera. That's key in determining it. The main risks that we assessed were delays to or unfavourable conditions of approvals from the statutory bodies-environmental, design, planning and construction works approvals-pressure from states, councils, communities and property owners to enhance or modify the scope; delays to accessing parts of the alignment to actually commence and progress construction; unexpected technical matters; and time. Time is a big risk for a really complex long infrastructure project like Inland Rail. Senator McKENZIE: You did that work internally yourselves. How many staff were involved in that within your organisation? Ms McDougall: Yes, we did do the work internally. We did use some consultants to help build the estimate. I'd have to take- Senator McKENZIE: It's quite technical work that you've just outlined. Ms McDougall: Absolutely. Senator McKENZIE: I'm sure you've got some great staff, but that's pretty serious. Who were the consultants you used? Ms McDougall: I'll have to take that on notice. One consultant that we did use was North Projects, who are a specialist estimating firm. I would also have to take on notice the number of staff internally who contributed to the estimate. Senator McKENZIE: How much did North cost to get this done? Ms McDougall: Again, I'll have to take that on notice, and I can treat that as a priority. I just don't have the information in front of me. Senator McKENZIE: Usually, at estimates we want to know what you procured, when, why and how much it cost, for future reference. There was more than north-are there two or three or four? Ms McDougall: Again, I'll have to take that on notice.

Answer

Please see attached PDF.