Question
1. Can Snowy Hydro confirm the exact date on which the Kurri Kurri Power Station will reach full commercial operation? 2. Is Kurri Kurri intended to provide firming or direct supply to the Tomago Aluminium Smelter, following the announcement from the Prime Minister that a deal is being finalised to find cheaper energy for the smelter, on 12 December 2024. 3. If Snowy is intended to provide Tomago energy will Snowy Hydro charge Tomago a commercial rate for firming services provided by Kurri Kurri, or is the taxpayer subsidising this support? What is the value of any subsidy? 4. Have you calculated the emissions when running Kurr Kurri on diesel, and what are those emissions?
Answer
Please see attached answer.