Bungendore Road - Macs Reef Road - BYWONG - 123120-23NSW-BS
Question
1. The Black Spot Program Project ID 123120-23NSW-BS was due to be completed in December 2025. The most recent project status update states that the project is ''under construction''. a. Can the Department provide an explanation as to why the project has not been completed? i. If not, why not? b. Has there been any modelling conducted to determine the revised expected finish date? i. If not, why not? ii. If yes, when is the project due to be completed? c. Has the entirety of the Australian Government's $1,994,710 contribution to the project been released to the state? i. If not, how much of it has been released to date? When is the remaining amount expected to be released?
Answer
Please see PDF attachment.