Old Pitt Town Road - Fontana Drive, Terry Road - BOX HILL - 126331-24NSW-BS
Question
1. The Black Spot Program Project ID 126331-24NSW-BS was due to be completed October 2025. According to the Investment Infrastructure website, the project status was updated on 27 November 2025, leaving the expected finish date as October 2025 despite the project still being under construction. a. Was the project started in July 2024 as expected? i. If not, why not? ii. How delayed was the project's commencement? b. Has any modelling been done to ascertain the revised project end date? i. If not, why not? ii. If yes, what is the revised project end date? How was this determined? c. Has the entirety of the Australian Government's $1,000,000 contribution to the project been released? i. If not, how much of it has been released to date? When is the remaining amount expected to be released?
Answer
Please see PDF attachment.