Clarencetown Road Gully Trail Road to 2.3km south of Timbertop Road GLEN OAK - 126399-24NSW-BS
Question
1. The Black Spot Program Project ID 126331-24NSW-BS was due to be completed in April 2026. According to the Investment Infrastructure website, the project status was updated on 20 January 2026, extending the project completion date to June 2026, and leaving the project status as ''not started''. a. Can the Department provide an explanation as to why the project has not started? i. If not, why not? b. How was the project's revised completion date determined? i. Does the Department anticipate that the expected completion date will be delayed further? c. Has the entirety of the Australian Government's $1,356,000 contribution to the project been released to Port Stephens Council? i. If not, how much of it has been released to date? When is the remaining amount expected to be released?
Answer
Please see PDF attachment.