Fuel Transformation Project
Question
The Fuel Transformation Project aims to further reduce risk to the ADF Fuel Network and Fuel Supply Chain. It will upgrade and/or remediate fuel installations across Australia to increase resilience of the Fuel Network, reduce total cost of ownership, and improve industry collaboration in delivering an assured fuel network. 1. What?s the status of Tranche 2 of the Fuel Transformation Project? 2. The plan for FY 2025-26 had the project spending $144.7 million, however the expenditure has only been a little under $29 million. Why the delta? 3. What?s the total expenditure to date? 4. Why is the project behind schedule? a. What are the causes of the delays? 5. What will the overall cost impact to the project be of the delays? 6. The total estimated expenditure last year was $286.9 million, in the 2026-27 portfolio budget statement that has gone up to $351.7 million, why the $65 million increase?
Answer
Please see attached answer.