Late Contract

View on aph.gov.au (opens in a new tab)
Status: Answered, finished
Asked by: Senator Jessica Collins
Type: Asked at a hearing
Agency: Department of Defence
Question No: 3
Asked: 4 Sept 2026
Answered: 21 Oct 2026

Question

Chair: So Defence engaged JLL on 21 April this year to conduct a valuation at a cost of $74,000. That's contract number CN4246611. What were they valuing? Ms Perkins: We'll see if we can get details on that. As I've described, JLL is a whole-of-Government provider, so we use JLL for many things. In addition to the work that the Committee has been focused on, we are transacting property business around the country all the time. So I would just want to be clear about what particular body of work that engagement might refer to. Chair: If somebody can get back to us in the next 10 minutes that would be terrific. There's a requirement for contracts to be published on AusTender within 42 days, which for this particular contract would have been 2 June. Most contracts are reported well before the due date. So I'm just trying to understand why, on this particular contract, it was reported late. It was reported two days after it was due. Ms Perkins: I couldn't say, but we can certainly enquire. Chair: To put that into context, on 2 June we saw you at Estimates. Two days later, the contract is reported two days late. So we're trying to understand whether it's - I don't know. Would you say that that's usual practice?

Answer

Contract Number 4246611 relates to work undertaken to value land that is unrelated to the Defence Estate Audit. The late publication of the contract on AusTender was an oversight, which resulted from an unexpected delay in the commencement of the contracted work.

Comments · 0

Loading...

Loading comments...