Make-good obligations, the current or estimated financial liability and any agreed variations

View on aph.gov.au (opens in a new tab)
Status: Answered, finished
Asked by: Senator Jacqui Lambie
Type: Asked at a hearing
Agency: Department of Defence
Question No: 18
Asked: 22 Oct 2026
Answered: 18 Nov 2026

Question

Senator Jacqui Lambie: Okay. I'll send these questions on. These are cost savings ones, so I won't hold you guys up, or the committee. I want to go into the leased properties again. I previously asked about the make good obligations against leased properties and what the total liability for those make good obligations is. The response I received was that any obligations to Defence's move off leased divestment sites will depend on the conditions of the lease and how the lease was concluded. So my question is: what are the make good obligations attached to each of the leased properties identified for divestment, and what is the financial liability associated with meeting the make good obligations for each of those properties? Do you think I can get it that way? Mr Peter West: I will take that question on notice, but I will add that, obviously, the make good obligations depend on the original contract itself but also on the exit negotiations. So, for example, at Training Ship Barwon the make good obligations meant that we were able to leave the building on the site because the site owner wished to retain the building. Therefore, we didn't have to knock that building down. But we are removing the pier from the site, which the site owner asked us to do under our make good obligations. So it depends on what the specifics of that lease require. But also then we would negotiate as we exit that lease as to what is actually required to make good because on numerous occasions we found that the owner would like to retain structures or improvements that have been made to the site rather than us removing them. Senator Jacqui Lambie: Okay. So you think we're going to have the previous stuff that has already been agreed on before you go down there and agree on more stuff if that means that you have to keep the building or whatever. Can we see the original obligations to each one of those leased places that you have? Mr Peter West: We'll take that on notice.

Answer

Make-good obligations are only fully known once negotiations have been finalised with the landlord of a particular site. The standard make good obligations on Defence as the Tenant are: 1. For a lease over the whole premises: a. Defence must remove any of its property or structures on the licenced area (if any). Defence must yield the premises and fixtures in a good and tenantable repair and condition, fair wear and tear accepted, free from rubbish, and remove signs and notices, repairing any damage caused by removal and transfer utilities/services to the Lessor; or b. Defence is required to remove moveable property and chattels at the end of the lease, and make good the land to the satisfaction of the Lessor. Built structures may be left in place unless they contain asbestos or are of no use to the Lessor and removal is specifically requested. 2. For a land lease: a. Where Defence improved the site by building works, Defence must deliver up the land in good and tenantable repair and condition, having regard to the condition on commencement of the lease, fair wear and tear excepted. 3. Where the Lease is silent on make-good: a. Make-good needs to be negotiated with the Landlord. b. Defence has the option to negotiate and pay the Licensor in lieu of make-good.

Comments · 0

Loading...

Loading comments...