Crib Point Primary School

School page (opens in a new tab)
Stage: Complete, finished
Address: 70 Milne St, Crib Point 3919
Projects: 2

Every project at this school is complete.

Inclusive Schools Fund

Complete
Start: Q4 2018
Finish: Q3 2019

In 2018, $117,400 was allocated to the school in Round 4 of the Inclusive Schools Fund.

We built a playground and surrounding sensory gardens. The playground includes tactile elements to encourage exploratory play, with a number of spaces to sit, regather, rest and reflect.

Minor Capital Works Fund

Complete
Start: Q4 2020
Finish: Q2 2021

In the 2020 Minor Capital Works Fund the school was allocated $88,625.

We helped the school to refurbish the roof of the senior school building and construct a covered walkway.