Merri Creek Primary School

School page (opens in a new tab)
Stage: Design, still live
Address: Miller St, Fitzroy North 3068
Projects: 2
State budget: $5.4 million, completion Q2 2027

Upgrade and Modernisation - Next Stage

Upgrade and Modernisation

Design
Start: Q2 2022
Finish: Q3 2027

In the 2022–23 State Budget, this school received $5.352 million.

We are modernising the school to give students better learning opportunities. In this significant upgrade we will:

- refurbish part of the existing heritage building (Block A)

- build a new rooftop learning space.

Upgrade and Modernisation

Complete
Start: Q2 2017
Finish: Q4 2019

In the 2017–18 State Budget, $3.9 million was allocated to the school.

We upgraded and modernised the school. This project delivered a new 2-storey junior school building.