Essendon North Primary School

School page (opens in a new tab)
Stage: Planning, still live
Address: 112 Keilor Rd, Essendon North 3041
Projects: 4
State budget: $24 million, completion Q3 2029

Upgrade and Modernisation

Planning
Start: Q2 2026
Finish: Q3 2029

In the 2026–27 State Budget, the school received $24.005 million.

We're upgrading the main classroom wing. This will give students more modern learning spaces.

Minor Capital Works Fund

Complete
Start: Q2 2022
Finish: Q2 2024

In the 2022–23 State Budget the project received $882,627 from the Minor Capital Works Fund.

We replaced the current student toilet block with a new construction to improve amenity, cleanliness and hygiene.

This work was supported by our Minor Capital Works Fund – a program for small building projects that make a big difference in our schools.

Inclusive Schools Fund

Complete
Start: Q4 2019
Finish: Q3 2021

In 2019, $200,000 was allocated to the school in Round 5 of the Inclusive Schools Fund.

We built an inclusive outdoor learning and sensory play area.

School Pride and Sports Fund

Complete
Start: Q4 2018
Finish: Q4 2019

In the 2018–19 State Budget, $411,300 was allocated to the school through the School Pride and Sports Fund. In the 2019–20 State Budget, a further $440,621 was allocated to the school through the School Pride and Sports Fund.

​We upgraded the school oval by laying synthetic turf and completing landscaping.