Aberfeldie Primary School

School page (opens in a new tab)
Stage: Complete, finished
Address: 1 Doone St, Essendon 3040
Projects: 3

Every project at this school is complete.

Upgrade and Modernisation

Complete
Finish: Q1 2019

The 2016–17 State Budget allocated $1.13 million funding to this school. The school received an additional $1.4 million in the 2018–19 State Budget.

We undertook modernisation works to upgrade existing school facilities​. This included refurbishments to student toilets, roofing, the hall and teaching spaces. Landscaping work was also undertaken throughout the site.

Inclusive Schools Fund

Complete
Start: Q4 2018
Finish: Q4 2019

In 2018, $100,000 was allocated to the school in Round 4 of the Inclusive Schools Fund.

We helped upgrade the outdoor sensory learning and leisure space with new garden beds, quiet areas and a sheltered structure.

Minor Capital Works Fund

Complete
Start: Q2 2022
Finish: Q1 2023

In the 2022–23 State Budget the project received $191,127 from the Minor Capital Works Fund.

We refurbished the staff toilets and the accessible toilets.