Box Hill North Primary School
Capital Works Fund
Through the 2025–26 round of the Capital Works Fund, the project received $499,641.
We are refurbishing the school's student toilets. This will make them more pleasant and improve cleanliness and hygiene.
Our Capital Works Fund is supporting this work. It provides funding for smaller building projects that make a big difference in our schools.
Upgrade and Modernisation
From the 2020–21 Infrastructure Planning and Acceleration fund, the school was allocated $422,000 in planning funding. In the 2020-21 State Budget, the school received at least $3.418 million from a pool of more than $85 million to expand seven schools in high-growth areas.
We modernised and expanded this school.
We constructed a classroom block that has eight new learning areas. We also relocated and refurbished the administration area.
The project has created an extra 100 places for local children.