Baringa Special School

School page (opens in a new tab)
Stage: Complete, finished
Address: 47 Staff St, Moe 3825
Projects: 2

Every project at this school is complete.

Upgrade and Modernisation – next stage

Upgrade and Modernisation

Complete
Start: Q4 2020
Finish: Q2 2024

In the 2020–21 State Budget, the school received $13.706 million.

We built on the upgrades and modernisation we completed in 2019 by constructing additional permanent buildings.

Block A has primary learning classrooms, and student and staff spaces. Block B is a secondary learning centre with classrooms, student and staff spaces, library, canteen and kitchen.

The buildings have covered links and landscaped areas, including a new car park.

Upgrade and Modernisation

Complete
Finish: Q1 2019

In the 2016–17 State Budget, $3 million was allocated to the school.

We provided new facilities and completed maintenance work on roofs at the school.

We delivered:

- a new multi-purpose hall that has 6 general purpose classrooms, quiet and group student workspaces, staff collaboration rooms and a consultation room

- new outdoor junior play spaces and landscaping that include outdoor and undercover learning spaces, and accessible staff and student facilities.