Skip to main content

Chalcot Lodge Primary School

School page (opens in a new tab)
Stage: Complete, finished
Address: 15A Primrose Hill Close, Endeavour Hills 3802
Projects: 3

Every project at this school is complete.

Capital Works Fund

Complete
Start: Q4 2024
Finish: Q1 2026

Through the 2024–25 round of the Capital Works Fund the project received $499,598.

We refurbished the school's student toilets. This makes them more pleasant, and improves cleanliness and hygiene.

Our Capital Works Fund supported this work. It provides funding for smaller building projects that make a big difference in our schools.

Minor Capital Works Fund

Complete
Start: Q4 2020
Finish: Q4 2022

In the 2020 Minor Capital Works Fund, the school was allocated $351,665.

We constructed a series of covered walkways to provide protection against the weather.

Inclusive Schools Fund

Complete
Start: Q4 2018
Finish: Q2 2020

In 2018, $175,500 was allocated to the school in Round 4 of the Inclusive Schools Fund.

We created an indoor inclusive space with materials to stimulate the senses, such as colours, textures and vegetation. It also has suspended play nets, a grassy hill, a tunnel and a covered teaching space with a performance area.