Stage: Complete, finished
Address: 30-60 Withers Way, Eltham 3095
Projects: 2
State budget: $8.9 million, financial completion Q3 2027

Every project at this school is complete.

Upgrade and Modernisation – science facilities

Upgrade and Modernisation

Complete
Start: Q2 2023
Finish: Q2 2026

In the 2023–24 State Budget the school received $8.94 million.

We upgraded and modernised the science areas to give students better learning opportunities.

Upgrade and Modernisation

Complete
Finish: Q2 2020

In the 2016–17 State Budget, $12 million was allocated to schools for planning, including Eltham High School. In the 2017–18 State Budget, $1.5 million was allocated to this school for capital works and $3.37 million through the Shared Facilities Fund.

We redeveloped Eltham High School's sports facilities in partnership with Nillumbik Shire Council.

We installed lighting at the sports oval and increased the number of multi-sport courts to include 6 tennis courts and 4 netball courts. We also resurfaced 2 existing outdoor netball/basketball courts.

To complement these facilities we also built new clubrooms with unisex change facilities, a canteen, storage, undercover area, and improved car parking for the sports complex.

For more information visit the Shared Facilities Fund . ​

Previous projects

A previous modernisation project was completed at Eltham High School in 2 stages.

Stage 1 delivered an update to the performance arts centre, including the installation of ranked seating, completion of audio visual fitout, curtains and acoustic treatment. This was completed in August 2016.

Stage 2 redeveloped the school's science and maths facilities. It also included general facility improvement across the whole school, including new carpets, painting and blinds in learning spaces, renovations of toilet blocks in Block F, new fencing, a locker pavilion and landscaping around Block A.​​