Red Cliffs Secondary College

School page (opens in a new tab)
Stage: Complete, finished
Address: 55 Fitzroy Ave, Red Cliffs 3496
Projects: 3

Every project at this school is complete.

Capital Works Fund

Complete
Start: Q4 2024
Finish: Q4 2025

Through the 2024–25 round of the Capital Works Fund the project received $499,999.

We refurbished the school's student toilets. This make thems more pleasant, and improves cleanliness and hygiene.

Our Capital Works Fund supported this work. It provides funding for smaller building projects that make a big difference in our schools.

Minor Capital Works Fund

Complete
Start: Q4 2020
Finish: Q4 2022

In the 2020 Minor Capital Works Fund the school was allocated $179,120.

We helped the school upgrade irrigation systems on the front garden and oval.

Upgrade and Modernisation

Complete
Start: Q4 2017
Finish: Q2 2019

In the 2016–17 State Budget, $7.06 million was allocated to the school.

We upgraded and modernised the school. The upgrades included:

- a new senior centre

- staff administration spaces

- covered locker areas

- refurbishments to the maths hub, library and performing arts building.

The project focused on creating flexible learning spaces, improving connections between internal and external areas, and upgrading site infrastructure. ​ ​