Upgrade and Modernisation – Stage 3

Upgrade and Modernisation

Complete
Start: Q4 2020
Finish: Q4 2024

From the 2020-21 Infrastructure Planning and Acceleration fund, the school was allocated $563,000 in planning funding. In the 2020-21 State Budget, the school received $7.559 million.

We continued to upgrade Hampton Park Secondary College, building on the works that were underway at the school.

Upgrade and Modernisation – Stage 2

Upgrade and Modernisation

Complete
Start: Q2 2019
Finish: Q4 2022

In the 2019–20 State Budget, the school received $3.9 million.

We upgraded and modernised the classrooms and facilities at Hampton Park Secondary College. We refurbished T-Block to create a STEAM/FabLab facility. This building includes new student toilets for the campus.

Upgrade and Modernisation – Stage 1

Upgrade and Modernisation

Complete
Start: Q2 2018
Finish: Q1 2022

In the 2018–19 State Budget, $2.62 million was allocated to the school.

We upgraded facilities at Hampton Park Secondary College, including refurbishing and modernising classrooms and converting the gym into a senior learning centre.

Inclusive Schools Fund

Complete
Finish: Q4 2017

In 2016, the school received $134,500 from Round 2 of the Inclusive Schools Fund.

​​We expanded and redesigned a disability and wellbeing space to include a new calming space, Indigenous sensory garden and music therapy hub.