Minor Capital Works Fund - 2022-23 State Budget - Wave Campus
Minor Capital Works Fund
In the 2022–23 State Budget the project received $111,397 from the Minor Capital Works Fund.
We refurbished the toilets in the hall at the school's Wave campus to improve amenity, cleanliness and hygiene. This work was supported by our Minor Capital Works Fund – a program for small building projects that make a big difference in our schools.
Minor Capital Works Fund - 2022-23 State Budget - Warrnambool Campus
Minor Capital Works Fund
In the 2022–23 State Budget the project received $499,397 from the Minor Capital Works Fund.
We refurbished the toilets and change rooms in the school's main campus multi-purpose hall. This has improved amenity, cleanliness and hygiene. This work was supported by our Minor Capital Works Fund – a program for small building projects that make a big difference in our schools.
Upgrade and Modernisation
In the 2016–17 State Budget, $5.1 million has been allocated to the school.
We have upgraded and modernised the facilities at the school. This included creating flexible learning spaces, improving connections between internal and external areas and upgrading site infrastructure.
Minor Capital Works Fund - Round 1 - Wave Campus
Minor Capital Works Fund
In the 2020 Minor Capital Works Fund, the school was allocated $366,165.
We repaired the roof of the school's WAVE building.