Stage: Complete, finished
Address: Blakeley Rd, Castlemaine 3450
Projects: 3

Every project at this school is complete.

Inclusive Schools Fund – Round 6

Inclusive Schools Fund

Complete
Start: Q2 2021
Finish: Q2 2024

In Round 6 of the Inclusive Schools Fund, this project received $72,253.

We built an outdoor inclusive learning space, including new play equipment and landscaping.

Upgrade and Modernisation – Stage 3

Upgrade and Modernisation

Complete
Start: Q2 2018
Finish: Q1 2021

The school has received an additional $12.256 million in the 2018–19 State Budget and through the Planned Maintenance Program.

We completed Stage 3 of the upgrade and modernisation at the school. This completes the second phase of the Performers Precinct, as well as the administration area and library and artisans precincts​.​

Upgrade and Modernisation – Stage 1 and 2

Upgrade and Modernisation

Complete
Finish: Q4 2017

In the 2013–14 State Budget, $7 million was allocated to the school. In the 2014–15 State Budget, $5.5 million was allocated to the school. In the 2015–16 State Budget, a further $2.5 million was allocated to the school.

W​​e are consolidating Castlemaine Secondary College onto one site on Blakely Road, replacing existing buildings in 4 stages to develop 4 distinct learning precincts.​ ​

Stages 1 and 2 involved:

- Stage 1 – The Wellbeing Centre

- Stage 2 – The Engineers' Precinct

- Stage 2B – Phase 1 of the Performers' Precinct.