Camberwell Primary School

School page (opens in a new tab)
Stage: Construction, still live
Address: 290 Camberwell Rd, Camberwell 3124
Projects: 4
State budget: $9.7 million, completion Q3 2026

Upgrade and Modernisation – main building and toilet block

Upgrade and Modernisation

Construction
Start: Q2 2023
Finish: Q4 2026

In the 2023–24 State Budget the school shared in $24 million allocated for planning. In the 2024-25 State Budget, total project funding of $9.7 million was announced.

We are upgrading the school's main building by refurbishing 5 classrooms, the well-being spaces and a reflection room in the east wing. We are also adding a classroom and science room in the west wing.

We are also building more toilets, a new front entry with an accessible ramp and landscaped courtyard, and outdoor learning areas.

Minor Capital Works Fund

Complete
Start: Q2 2022
Finish: Q2 2024

In the 2022–23 State Budget the project received $367,127 from the Minor Capital Works Fund.

We refurbished the student toilets in the school's main administration building to improve amenity, cleanliness and hygiene. This work was supported by our Minor Capital Works Fund – a program for small building projects that make a big difference in our schools.

Upgrade and Modernisation

Complete
Start: Q4 2020
Finish: Q4 2023

In the 2020–21 State Budget, the school received $709,000. A further $1,056,137 was allocated to the school in 2021.

We upgraded and modernised the school, converting the car park to more open space.

Inclusive Schools Fund

Complete
Start: Q4 2018
Finish: Q1 2020

In 2018, $180,500 was allocated to the school in Round 4 of the Inclusive Schools Fund.

We built an outdoor sensory learning space that is used for lessons and free play. This was part of a wider development that included upgrading the school’s library and a new building that we completed in 2018.