Stage: Construction, still live
Address: Brentnall Road, Croydon 3136
Projects: 3
State budget: $12.7 million, completion Q3 2027

Upgrade and Modernisation – Stage 3

Upgrade and Modernisation

Construction
Start: Q2 2023
Finish: Q2 2027

In the 2023–24 State Budget the school shared in $24 million allocated for planning. The 2025-26 State Budget announced total project funding of $12.7 million. This includes earlier planning funding.

Following planning funding, we will upgrade and modernise the school. We are completing Stage 3 upgrades at this school.

This includes:

- building a new performing arts space

- creating a new oval

- improving car parking.

Upgrade and Modernisation – Stage 2

Upgrade and Modernisation

Complete
Start: Q2 2018
Finish: Q2 2020

The 2018–19 State Budget allocated $11.05 million to the project. This project also received $1.5 million from the Shared Facilities Fund.

​We built a Science Technology Engineering Arts and Maths (STEAM) building and a competition-standard basketball stadium (developed with Sports and Recreation Victoria and the Kilsyth Basketball Club).​

This project, designed by Y2 Architecture, won 'Best School Project - Above $5 million' at the 2018 Victorian School Design Awards .

Upgrade and Modernisation – Stage 1

Upgrade and Modernisation

Complete
Finish: Q2 2018

The 2015–16 State Budget allocated $500,000 in planning funding. The school has received an additional $17.9 million in the 2016–17 State Budget.

We rebuilt Melba Secondary College to bring the junior and senior campuses together on one site, giving students state-of-the-art facilities.

The 2016–17 State Budget funding built new facilities, including three double-storey buildings to provide space for growing enrolments. Students are now able to collaborate in flexible modern learning spaces, and the school has gained new administration offices, a library and cafeteria.

The first stage of the rebuild of Melba Secondary College, completed in June 2018 for $18 million, won the award for Best School Project – Above $5 million at the 2018 Victorian School Design Awards​.