Sydenham-Hillside Primary School

School page (opens in a new tab)
Stage: Complete, finished
Address: Wattle Valley Dr, Sydenham 3037
Projects: 3
State budget: $9.5 million, financial completion Q2 2027

Every project at this school is complete.

Upgrade and Modernisation – Hillside and Sydenham Campuses

Upgrade and Modernisation

Complete
Start: Q2 2023
Finish: Q1 2026

In the 2023–24 State Budget the school received $9.5 million.

We upgraded buildings and installed new fencing across both campuses.

We resurfaced the oval and upgraded staff toilets at the Hillside campus.

We upgraded the soccer pitch with synthetic turf at the Sydenham campus.

Minor Capital Works Fund – Hillside Campus

Minor Capital Works Fund

Complete
Start: Q2 2022
Finish: Q3 2024

In the 2022–23 State Budget the project received $426,627 from the Minor Capital Works Fund.

We refurbished toilets and showers in the Hillside campus gymnasium to improve amenity, cleanliness and hygiene.

This work was supported by our Minor Capital Works Fund – a program for small building projects that make a big difference in our schools.

Minor Capital Works Fund – Sydenham Campus

Minor Capital Works Fund

Complete
Start: Q2 2022
Finish: Q2 2024

In the 2022–23 State Budget the project received $478,627 from the Minor Capital Works Fund.

We refurbished the toilets in the administration building and partially refurbished the toilets in the gymnasium, to improve amenity, cleanliness and hygiene.

This work was supported by our Minor Capital Works Fund – a program for small building projects that make a big difference in our schools.