Question on Notice 169/2026: Rockhampton Ring Road project

View Answer (opens in a new tab)
Answered: Yes
Question Number: 169
Year: 2026
Asked By: Mr B Mellish
Minister Responsible: Minister for Transport and Main Roads (Hon B Mickelberg)
Asked Date: 4 Mar 2026
Answer Due: 7 Apr 2026
Date Tabled: 7 Apr 2026

Topic

Rockhampton Ring Road project

Question

With reference to the Rockhampton Ring Road project, with construction commenced on the main works package in August 2025— Will the Minister advise (a) what is the current budget and timeframe for the project and (b) is this cost inclusive of the 'Alexandra St overpass' section being delivered as an overpass or as an intersection?

Full text in the tabled PDF (opens in a new tab).