Logan and Gold Coast Faster Rail
Description
Unlocking additional train services to meet the growing travel demand between Brisbane and the Gold Coast.
Timeline
- Done Business case and early planning 2021
- Done Community engagement September and October 2021
- Done Detailed design - Loganlea Station Relocation (LSR) 2021-2023
- Done Reference design refinement - Logan and Gold Coast Faster Rail (LGC) project 2021-2023
- Done Community engagement 13 November - 10 December 2023
- Done Contract award - LSR September 2024
- Done Contract award - Open Level Crossing Removal (OLCR) package September 2024
- Done Design and pre-construction contract award - LGC Rail package March 2025
- Done Community engagement on Kuraby and Bethania level crossing removals September and October 2025
- Upcoming Construction - Loganlea Station Relocation In progress
- Done Engagement for station designs from Kuraby to Kingston November and December 2025
- Done Community engagement on station design for Edens Landing
- Done Community engagement on station design for Beenleigh
- Upcoming Community engagement on station design for Holmview Mid-2026
- Upcoming Construction - OLCR package In progress
- Upcoming Construction - LGC Rail package Site establishment is currently underway. Major construction will begin later in 2026.